Edit activities

If you want to use the "Attendance clock" function, one of the productive activities and one of the non-productive activities must have the default value "1".

You cannot assign the value "1" to several activities, otherwise no clear assignment is possible. All other productive activities can either have no value or the value "0".

The unproductive activity that has the value "1" is stored in the break times of the attendance clock. The productive activity with the value "1" is stored in the working time of the attendance clock. The activities can be changed under "Description" in the weekly report.

Under Maingroup affiliation, add the desired main groups to the activity.